Construction Proposal Evaluation
Contract: AMCMS Fire Sprinkler Main Piping Replacement
Item Evaluated Standard Automatic Fire International Fire Simplex Grinnell
1.0 Price: $36,000.00 x 1/$ _________ x 82 = 82 76.26 43.46
(Lowest Price) (Proposers Price) (Maximum Points)
2.0 Schedule: Does schedule comply with requirements?
(Yes-2) (No-0 or disqualify) = 2 2 2
3.0 Proposed Quality: Does proposal meet requirements?
(Yes-1-10) (No-0 or disqualify) = 10 10 10
4.0 Reference Checks: Were reference checks acceptable?
(Yes-2) (No-0 or disqualify) = 2 2 2
5.0 Previous Performance: Did Contractor perform
Satisfactorily in previous contracts?
(Yes-2) (No-0 or disqualify) = 2 2 2
6.0 Safety: Does Contractor have a satisfactory safety?
Program and experience working in occupied
Total Points by Contractor: (Sum of above - 100 Max.) 100 94.25 61.46 ________________________________________________________________________________________________________________________________
Recommended Contractor: Standard Automatic Fire Basis of selection - most points which provide best value to district
EVALUATORS:
George Mc Lean Date: 04-28-03
Mark Pantel Date: 04-28-03